I-25 Trinidad under construction - a Colorado Department of Transportation Project Website
I-25 Trinidad under construction I-25 Trinidad under construction - click for the latest construction bulletin and traffic news
Home
Latest News
Project Information
Community Relations
Contact Us
Project Progress
Citizens Online - sign up to receive 
email news, updates and bulletins.

Progress Photos: 2008

    December 2008

      arrowFinal grading of the non-structure portion of NB I-25
      I-25 Trinidad construction project
        arrowPaving operations lay 12" of Portland Cement Concrete Paving
      I-25 Trinidad construction project
      arrowThe contractor's concrete paving machine in action laying pavement
      I-25 Trinidad construction project
        arrowTrucks deliver pavement to the back of the paving machine
      I-25 Trinidad construction project
      arrowFrom this view of the viaduct the temporary stiffeners are visible between the walls of the box girders I-25 Trinidad construction project   arrowWorkers will soon be preparing the girders to receive formwork for placing the deck
      I-25 Trinidad construction project
      arrowConstruction team pre-erection meetings ensure that girder placement proceeds safely and efficiently
      I-25 Trinidad construction project
        arrowCranes set the large variable depth girder segments cantilevered from piers near the railroad I-25 Trinidad construction project
      arrowThese variable depth girders are used to create the long span necessary to cross the railroad
      I-25 Trinidad construction project
        arrowThe deepened section of the variable depth girder occurs over the supporting pier
      I-25 Trinidad construction project
      arrowWorkers re-install the original historic brick pavers in Commercial Street which were removed and stored at the beginning of the project
      I-25 Trinidad construction project
        arrowMany of Trinidad's brick paved streets were declared protected historic components of the Corazon de Trinidad Historic District in 1977
      I-25 Trinidad construction project

    October 2008

      arrowNorthbound I-25 north of Commercial Street at final grade and ready for paving
      I-25 Trinidad construction project
        arrowBarrier reinforcing waiting for concrete on the viaduct and the Commercial Street off-ramp
      I-25 Trinidad construction project
      arrowPlacement of steel reinforcement at Commercial off-ramp
      I-25 Trinidad construction project
        arrowGirders at Nevada Ave
      I-25 Trinidad construction project
      arrowGirders over College St
      I-25 Trinidad construction project
        arrowGirders north of Railroad tracks
      I-25 Trinidad construction project
      arrowNorthbound I-25 north of Van Buren at final grade and ready for paving
      I-25 Trinidad construction project
        arrowMSE walls and abutments near final heights at Main Street bridge
      I-25 Trinidad construction project
      arrowSlip formed Type 7 barrier on the Purgatoire River bridges
      I-25 Trinidad construction project
         
      arrowThe Main Street overpass MSE abutments near completion.
      I-25 Trinidad construction project
        arrowWork continues on the MSE wall leading up to the Main Street overpass.
      I-25 Trinidad construction project
      arrowThe contractor continues to place girder segments for the viaduct and the Commercial Street off-ramp.
      I-25 Trinidad construction project
         

    September 2008

      arrowConstruction cranes prepare to set girders on the south end of the viaduct which includes the long span that crosses the railroad.
      I-25 Trinidad construction project
        arrowWorkers measure and fabricate the temporary steel-cross bracing and shoring towers that will secure the concrete girders during construction.
      I-25 Trinidad construction project
      arrowCranes place the first segment of the pre-cast post-tensioned segmental concrete box girder.
      I-25 Trinidad construction project
        arrowThe concrete segments will be tied together or 'tensioned' after all the segments are in place.
      I-25 Trinidad construction project
      arrowThe girder is tensioned with heavy cables threaded through reinforced steel ducts which are cast into the walls and floor of the segments.
      I-25 Trinidad construction project
        arrowTemporary shoring towers support one end of the segment until adjoining segments are placed and the girder is tensioned.
      I-25 Trinidad construction project
      arrowThe post-tension girder allows a long span to clear the railroad with minimal structure depth and cost. Note the duct openings at the end of the segment (floor of girder) through which the cables will be threaded.
      I-25 Trinidad construction project
        arrowWorkers mount temporary steel cross-bracing to prevent movement until the adjoining segments and deck are in place.
      I-25 Trinidad construction project

    August 2008

      arrowCrews place reinforcing steel for the concrete deck of Unit 3 of the Northbound viaduct. The deck of the viaduct is poured in monolithic units.
      I-25 Trinidad construction project
        arrowView of deck reinforcing steel with a noticeable super-elevation slope for the roadway curve.
      I-25 Trinidad construction project
      arrowFinal inspections and adjustments to the steel prior to placing or 'pouring' concrete.
      I-25 Trinidad construction project
        arrowA concrete pumper truck begins pumping fresh concrete into the Unit 3 deck.
      I-25 Trinidad construction project
      arrowWorkers vibrate the fresh concrete between the reinforcing steel bars to prevent voids.
      I-25 Trinidad construction project
        arrowOnce the pour reaches the proper level workers finish the surface of the new deck.
      I-25 Trinidad construction project
      arrowInspectors perform tests on each load of concrete to ensure quality.
      I-25 Trinidad construction project
        arrowAs concrete continues to arrive during the night, inspectors continue to test.
      I-25 Trinidad construction project
      arrowThe concrete pour (monolithic) for Unit 3 continues through the night until the unit is complete.
      I-25 Trinidad construction project
       
      arrowEarth movers lay in the final lifts for the Commercial Street off-ramp between MSE walls.
      I-25 Trinidad construction project
        arrowThe Commercial Street ramp at rough grade, covered and waiting for roadway surfacing.
      I-25 Trinidad construction project
      arrowNew curb and gutter completed on the Commercial Street exit ramp.
      I-25 Trinidad construction project
         
      arrowThe last of the Northbound viaduct piers ready for girders.
      I-25 Trinidad construction project
        arrowMain Street abutment ramp walls waiting for final I-25 grade and upper layers of MSE panels.
      I-25 Trinidad construction project

    July 2008

      arrowPre-cast bridge deck panel installation on the I-25 NB viaduct.
      I-25 Trinidad construction project
        arrowPre-cast bridge deck panel installation on the I-25 NB viaduct.
      I-25 Trinidad construction project
      arrowConcrete paving on NB I-25 to Main Street off-ramp.
      I-25 Trinidad construction project
        arrowNorthbound Main Street on-ramp and MSE retaining wall.
      I-25 Trinidad construction project
      arrowView from under the Commercial Street off-ramp.
      I-25 Trinidad construction project
        arrowCommercial Street off-ramp.
      I-25 Trinidad construction project

    June 2008

      arrowContractor placing Portland Cement concrete paving and curb and gutter on Commercial Street.
      I-25 Trinidad construction project   I-25 Trinidad construction project
      I-25 Trinidad construction project   I-25 Trinidad construction project
      I-25 Trinidad construction project  
      See the Benefits to Trinidad page for more information about local contractors and suppliers.

    May 2008

      arrowPre-Cast Concrete Box Girders top viaduct piers near Commercial Street.
      I-25 Trinidad construction project
        arrowMSE retaining wall for the Main Street on-ramp nearing completion.
      I-25 Trinidad construction project
      arrowConstruction cranes place pre-assembled steel reinforcement into the forms of a Viaduct Pier.
      I-25 Trinidad construction project
         
      arrowMixer and Pumper trucks place concrete for the last of the Northbound Viaduct Piers.
      I-25 Trinidad construction project
        I-25 Trinidad construction project
      arrowWorkers place concrete paving and barriers on the Commercial Street Ramp
      I-25 Trinidad construction project
        I-25 Trinidad construction project

    March 2008

      arrowMainline Overpass at Main Street being prepared for deck placement.
      I-25 Trinidad construction project
        arrowNorth Abutment of the Mainline Viaduct from Commercial Street near the Amtrak Depot.
      I-25 Trinidad construction project
      arrowNorthbound Ramp Structure over Purgatory River from the SH 12 Extension bridge completed during Phase I of the project. I-25 Trinidad construction project    

    February 2008

      arrowWorkers use cranes to set concrete girders for the bridge at Northbound I-25 over Main Street.
      I-25 Trinidad construction project
        arrowNorthbound Viaduct and Northbound Commercial Street Off-Ramp.
      I-25 Trinidad construction project
      arrowNorthbound Viaduct and Northbound Commercial Street Off-Ramp. I-25 Trinidad construction project   arrowPurgatoire River Bridge Girders and Piers.
      I-25 Trinidad construction project
      arrowPurgatoire River Bridge North Abutment.
      I-25 Trinidad construction project
        arrowMain Street Northbound On-Ramp.
      I-25 Trinidad construction project
      arrowElectrical conduit installation at College Street. I-25 Trinidad construction project    


A Colorado Department of Transportation Colorado Department of Transportation project website.
Copyright © Felsburg Holt & Ullevig Felsburg Holt and Ullevig
webmaster@i25trinidad.com