Crews place reinforcing steel for the concrete deck of Unit 3 of the Northbound viaduct. The deck of the viaduct is poured in monolithic units.
| |
View of deck reinforcing steel with a noticeable super-elevation slope for the roadway curve.
|
Final inspections and adjustments to the steel prior to placing or 'pouring' concrete.
| |
A concrete pumper truck begins pumping fresh concrete into the Unit 3 deck.
|
Workers vibrate the fresh concrete between the reinforcing steel bars to prevent voids.
| |
Once the pour reaches the proper level workers finish the surface of the new deck.
|
Inspectors perform tests on each load of concrete to ensure quality.
| |
As concrete continues to arrive during the night, inspectors continue to test.
|
The concrete pour (monolithic) for Unit 3 continues through the night until the unit is complete.
| |
|
Earth movers lay in the final lifts for the Commercial Street off-ramp between MSE walls.
| |
The Commercial Street ramp at rough grade, covered and waiting for roadway surfacing.
|
New curb and gutter completed on the Commercial Street exit ramp.
| |
|
The last of the Northbound viaduct piers ready for girders.
| |
Main Street abutment ramp walls waiting for final I-25 grade and upper layers of MSE panels.
|