Construction continues and installation of abutment caissons for the I-25 bridge at Main Street is making progress.
|
| |
|
| |
|
| |
|
| |
|
|
A large crane lifts a new precast concrete storm sewer inlet into place at Main Street.
| |
Workers use the crane to make final elevation adjustments to the inlet before connecting pipe.
|
|
Workers tie the reinforcing steel cages for a viaduct pier column.
| |
Prefabricated form panels will be used to shape the concrete viaduct piers.
|
|
Form panels can be assembled used and then disassembled and used again on the next pier.
| |
Workers patch a pier form panel to ensure a smooth concrete finish.
|
|
An MSE or Mechanically Stabilized Earth wall being constructed at the Commercial Street Ramp.
| |
An MSE wall consists of a system of inter- locking precast concrete panels visible here.
|
Behind the MSE wall panels attached metal strips mechanically stabilize each successive layer of the earth fill giving this system its name.
| |
The front face of the MSE wall panels have been formed to create a pattern resembling an ashlar wall.
|
|
A Temporary Amtrak station is in place on the project and being readied for service.
| |
|